Portland Port's Berth Extension is Well Underway

The works to extend our main cruise berth; Outer Coaling Pier are well underway.  The piling for the outer dolphin is complete with piling for the inner dolphin being put in place at the moment.

Ian McQuade, General Manager – Commercial, at Portland Port commented,

“It is exciting for us and the wider community to watch the works progressing.  It is a feat of engineering with the average pile for this project, being 27 metres long.  Each pile was delivered to the port individually, which required careful planning and traffic management to ensure it went as smoothly as possible.  Once completed, we will be one of a small number of ports along the English Channel that can accommodate vessels with LOA’s of more than 340 metres.” 

When the extension has been completed, it will boast a new suite of mooring bollards, high capacity pneumatic floating fenders and a minimum water depth of 9.6m CD.  There are also plans to increase the minimum water depth to 10 metres.

As the cruise ships sailing the world continue getting larger, the new cruise berth and increased minimum water depth will allow Portland to accommodate some of the biggest cruise ships in operation.

Photograph taken by Ted Toop

Amy Sandford Smith: 21st Dec 2016 12:18:00

Other Recent News

NEW JOB VACANCIES

NEW JOB VACANCIES

The port currently has a vacancy for a full time Security Officer. Click on this story for more details.

Admin: 22nd Mar 2024 12:47:00

Buses vital for cruise ship visitsMaritime and Coastguard Agency leads counter-pollution exerciseVessel in distress? Your call can make the difference…NEW NOTICES IN FORCENew Fishing Regulation for Hamm BeachPort Signs Armed Forces CovenantPortland Harbour PatrolsHome Office Statement on the Bibby Stockholm 19th October 2023Record Double Day for Cruise Liners at Portland Port